Cheltenham

  • Top floor extension prior to fit out
    Top floor extension prior to fit out
  • Top floor extension prior to fit out
    Top floor extension prior to fit out

A shell in August; fitted out by Christmas… Steinhoff’s impressive new offices were tailored to suit in just 17 weeks, thanks to a close partnership and efficient working practices

Adding an extra floor to Festival House not only extended a successful commercial development in the heart of Cheltenham, it also became home for a prestigious international business.

Just weeks after planning permission was granted, the UK arm of global furniture business Steinhoff International had signed a lease and instructed that the new top floor be configured to meet their requirements.

Steinhoff’s exacting, high quality specification was detailed and demanding. Formal Investments recommended their established design team who rose to the challenge of providing the 7,716 sq ft office that Steinhoff desired, in an impressively short timescale.

Background

Festival House is situated in the expanding business district at the heart of Cheltenham. Following a major redevelopment, Festival House now provides high specification offices for an impressive range of tenants.

Key Facts

key Facts