Aviva - Festival House

Cheltenham

  • Before…
    Before…
  • After
    After
  • Before…
    Before…
  • After
    After

Totally stripped back to a bare shell and refurbished to the incoming tenant’s specification in less than 8 weeks

A lease was agreed with insurance giants Aviva for 3,459 sq ft on the first floor of Festival House.

The area was totally stripped back to a bare shell and fully refurbished, complete with raised access floor, ready for the client fit-out to accommodate 26 employees and completed within the 8 week timescale.

Background

Festival House is situated in the burgeoning business district in the heart of Cheltenham.

Following a major scheme of works it provides high specification office accommodation with impressive staffed reception, meeting rooms and conference facilities.

Key Facts